Copings are laid on a mortar base with 10mm joints. Lay the paving with a slope of 1cm per metre, on a lean mortar screed after pouring a concrete slab.
1.Coping laid flush with the paving.
2. Coping laid over the paving.
Levelling the mortar base using a straight-edge
Tamping the paving
Filling the joints and smoothing with a small trowel